A technician walks through a nearly empty factory hall past electrolyser units wrapped in plastic (illustration).
INDUSTRY TRENDS
9 min read

French hydrogen, rung by rung: announced, supported, decided, built

France’s energy plan aims for up to 4.5 GW of electrolysers in 2030 and rounds what is installed to zero. Between the two sit about 300 MW supported, 250 MW decided, one 200 MW plant under construction and about 50 MW running, each counted by a different publisher.

Evidence reviewed · November 20, 2026 · 13 sources

France's energy plan for 2026 to 2035, adopted by decree on 12 February 2026, has a row for hydrogen. It counts installed electrolysis capacity, the machines that split water into hydrogen with electricity. For 2023 the cell reads « 0 GW ». For 2030 it reads « Jusqu'à 4,5 GW » (up to 4.5 GW). For 2035, « Jusqu'à 8 GW » (Programmation pluriannuelle de l'énergie 2026-2035, summary table).

Between a target of up to 4.5 gigawatts and a starting point the State rounds to zero, where does French hydrogen actually stand, and which of the jobs it promises exist today?

French hydrogen is not one number but a ladder. Each rung is counted by a different publisher: what is announced, what the State has supported, what companies have decided to build, what is being built, and what is installed. The rungs are an order of magnitude apart. A reader who takes the top rung for the bottom one will look for jobs that do not yet exist, and miss the ones that do.

Five rungs, five publishers

The plan itself carries the figures; the decree that adopts it does not. Its first article states only « La programmation pluriannuelle de l'énergie est adoptée » (Décret n° 2026-76, 12 February 2026, Article 1). The adopted document then frames the 2030 and 2035 figures as ceilings. "Up to" is the plan's wording, and we keep it: a ceiling is not a commitment to build.

The same document describes the rung below. Since September 2020, it says, the national strategy « a déjà soutenu environ 300 MW de capacité d'électrolyse » (has already supported about 300 MW of electrolysis capacity), with State commitments « de près de 9 milliards d'euros d'ici à 2030 » (of close to €9 billion by 2030) (Programmation pluriannuelle de l'énergie 2026-2035). Supported means a grant or a contract was signed. It does not mean a machine is running.

The industry association counts the next two rungs. In its barometer of January 2026, France Hydrogène put projects at final investment decision or under construction at 250 MW, and installed electrolysis at 50 MW (France Hydrogène, Baromètre annuel 2025, 27 January 2026). Fifty megawatts is the reason the State's table can print zero gigawatts: one is a rounding of the other.

The table below sets the rungs side by side. We print each figure with its publisher and its date, and we do not draw them as one line. The State and the association count different things on different dates; joining their figures would invent a trend neither has published.

Read top to bottom, the table describes a narrowing. The 2030 ceiling is about fifteen times what the State says it has supported. What the State has supported is larger than what companies have decided to build. And what is installed is a fifth of what has been decided. We print no ratio beyond these orders of magnitude; the publishers do not.

One plant on the decided rung

Most of the decided rung is one project. Air Liquide describes its Port-Jérôme site in Normandy in plain terms: « Air Liquide Normand'Hy is a 200 MW PEM electrolyzer under construction ». The company states that it is « Planned to be commissioned in 2026 », that it will produce « around 28,0006 tonnes » of hydrogen per year, and that it is funded « within France 2030 », the State investment plan (Air Liquide, 10 April 2026).

Two hundred megawatts set against a decided rung of 250 MW makes the arithmetic of the next year simple. If Normand'Hy is commissioned, France's installed figure moves from a rounding error to a number the State's own table would have to print. If it slips, the installed rung stays where it is. We have not found an Air Liquide document stating that the plant is running, so this piece describes it as the company last described it: under construction.

Other projects sit on lower rungs. TotalEnergies has said that a first 20 MW phase of its Masshylia project at La Mède is targeted for 2029, and the company's release makes that target conditional (TotalEnergies, 25 November 2024). Lhyfe inaugurated a site at Buléon in Brittany able to produce up to 2 tonnes a day (Lhyfe, 15 December 2023). Small sites like Buléon are why the installed rung is not literally zero.

Named French projects and the rung each document places them on

Project (place)What the document printsRungDocument date
Air Liquide Normand'Hy (Port-Jérôme)200 MW PEM electrolyser under construction, commissioning planned 2026Under construction10 Apr 2026
TotalEnergies Masshylia (La Mède)First 20 MW targeted for 2029, conditionalAnnounced25 Nov 2024
Lhyfe (Buléon)Site inaugurated, up to 2 tonnes a dayInstalled15 Dec 2023
Genvia (Béziers)Stack pilot line inauguratedManufacturing pilot, not production capacity8 Jun 2023

Sources 6 Air Liquide S.A. · 7 Genvia · 11 TotalEnergies · 12 Lhyfe

The factories that were meant to supply the ladder

The plan also counts on French machine-makers. It sets an aim of « cinq gigafactories d'électrolyseurs » (five electrolyser gigafactories) (Programmation pluriannuelle de l'énergie 2026-2035). The record of the last three years runs the other way.

In February 2025, GTT announced a strategic review of its electrolyser subsidiary Elogen. Construction of the planned gigafactory at Vendôme was suspended, and up to 110 positions were affected (GTT, 10 February 2025).

In July 2025, McPhy's fate was settled in court. On 8 July, the Tribunal de commerce de Belfort approved the sale of McPhy's Belfort gigafactory, its technologies and its intellectual property to John Cockerill Hydrogen. The buyer took on « 51 personnes sur un effectif de 71 » (51 people out of a workforce of 71) in France, and the receivership was converted to liquidation (McPhy Energy, 8 July 2025). Press reports in May had described a liquidation coming; the judgment is the date of record, and it is the one we print.

The one opening on this side of the ledger is a pilot. Genvia, the solid-oxide electrolyser maker backed by the CEA and partners, inaugurated a stack pilot line in Béziers in June 2023, and said its first demonstration system would go to ArcelorMittal « in 2025 » (Genvia, 8 June 2023). A press report later gave a figure for State support and a construction date for a full factory. We found no Genvia or State document confirming either, so we print neither.

French electrolyser manufacturing, openings and closures

  1. 8 Jun 2023

    Genvia inaugurates its stack pilot line in Béziers

  2. 10 Feb 2025

    GTT suspends Elogen's Vendôme gigafactory; up to 110 positions affected

  3. 16 Apr 2025

    Updated national hydrogen strategy published

  4. 8 Jul 2025

    Belfort court: McPhy assets and 51 of 71 French staff to John Cockerill Hydrogen; liquidation

  5. 12 Feb 2026

    Energy plan adopted by decree: up to 4.5 GW in 2030, up to 8 GW in 2035

Sources 7 Genvia · 9 GTT · 8 GlobeNewswire · 5 Direction générale des Entreprises · 2 Légifrance (service public de la diffusion du droit)

France is not alone on the ladder

The European picture has the same shape. The International Energy Agency counts installed water electrolysis in the EU at « around 340 MW, significantly less than the interim target of 6 GW by 2024 » (International Energy Agency, Global Hydrogen Review 2025, p. 99). Its manufacturer table lists McPhy's liquidation in the second quarter of 2025 and the cancellation of Elogen's factory. The chart below uses the agency's two figures only; both come from the same page.

EU installed water electrolysis against the interim target, end of 2024

Interim EU target for 20246 GWInstalled in the EU, around340 MW
  • Interim EU target for 2024: 6 GW MW, as printed by the IEA ("around" kept in the label)
  • Installed in the EU, around: 340 MW MW, as printed by the IEA ("around" kept in the label)

MW, as printed by the IEA ("around" kept in the label)

Source 10 International Energy Agency

A French reader should take two things from the comparison. The gap between targets and machines is not a French failing alone. And the rung that matters for work in the next two years is the same everywhere: the plants that are being built, not the ones that are announced.

How to read the counts

The association has published an installed figure in each of its last three editions: 30 MW in its key figures for 2023 (France Hydrogène, Les chiffres clés, January 2024), 35 MW in its 2024 barometer (28 January 2025) and 50 MW in its 2025 barometer (27 January 2026). It is tempting to draw those three as a line. We do not, for a reason the editions themselves show: what they count alongside the installed figure changes from one to the next.

The rung above installed is the clearest case. The 2023 edition groups 300 MW in operation, under construction or at investment decision; the 2024 barometer groups 315 MW in service, under construction or at investment decision; the 2025 barometer counts 250 MW at investment decision or under construction. The first two include machines already running; the third does not appear to. A fall from 315 to 250 may be a change of definition rather than a loss of projects, and the documents do not settle which. We print each figure with its edition and leave the trend unwritten.

Station counts carry the same caution. The 2023 edition counts 69 stations open; the 2025 barometer counts 50 stations of more than 50 kg a day. These are not one fleet shrinking; they are two definitions. A reader comparing hydrogen across years should compare like with like, and when the publisher changes the measure, the honest result is two numbers and no line.

None of this is a criticism of the association, whose barometer is the only regular count of French projects we found. It is a reason to read each edition as a photograph, not as a frame of a film.

The State's figures need a similar reading. "Supported" in the plan is a cumulative count of what public money has backed since 2020. "Installed" in the same table is a point estimate for one year, rounded to the gigawatt. Both are true; they are simply not the same kind of number, and the ladder exists to keep them apart.

Jobs, rung by rung: what it means for your career

The association's last published count of employment is 6,300 direct jobs, within 16,400 jobs including indirect ones, for the reference year 2023 (France Hydrogène, Baromètre annuel 2024, 28 January 2025, citing a BDO study). The updated national strategy looks forward to 8,0005 direct jobs by 2030 (Direction générale des Entreprises, 16 April 2025). These two numbers measure different things, one counted and one hoped for, and we do not subtract one from the other.

What the ladder shows is where each kind of work sits. On the announced rung there are studies, permits and project development: engineering consultancies, grid-connection specialists and the people who prepare investment files. On the decided and construction rungs there are site engineers, electrical and instrumentation technicians, safety and commissioning teams, the trades a 200 MW plant needs to be built and switched on. On the installed rung there are operators and maintenance technicians, a smaller number of permanent posts that last the life of the plant.

The manufacturing rung is the one that has shrunk. Twenty of McPhy's seventy-one French staff did not move to the buyer, and Elogen's suspended factory affected up to 110 positions. For someone weighing a move into electrolyser manufacturing, the record since 2023 is a reason to look closely at who the employer is and what stage its factory has reached, not a reason to avoid the field.

For candidates, read the rung before the headline. A plant described as under construction, like Normand'Hy, is hiring for construction and commissioning now and for operations next. A project described as targeted or conditional is a project in development, where the roles are fewer and closer to engineering studies. Installed capacity of about 50 MW means that operations posts in electrolysis remain few. None of this is a vacancy; it is where to look.

For employers, the distance between the supported and the decided rungs is a planning risk. Supply contracts priced on a 4.5 GW ceiling may meet a market closer to the hundreds of megawatts that have been decided. The figures a supplier should plan on are the ones counted at investment decision, not the ceiling.

For decision-makers, the record supports one request: publish one ladder. The State's plan prints the announced and supported rungs; the association prints the decided and installed ones. A single public table, dated and kept up to date by one publisher, with the same definitions from one edition to the next, would let anyone see the ladder move.

CareerOn's view is that in French hydrogen, the rung tells a job-seeker more than the target. Construction and commissioning roles exist today around the plants being built; operations roles follow when they are switched on; manufacturing roles depend on a few employers whose record since 2023 is mixed. We have not placed a CareerOn practice exercise that matches these roles in this piece, so none is offered here; we record that as a gap in our catalogue.

The ceiling is the number that makes the news. The ladder is the part that tells you where the work is, and in 2026 the rung to watch is a single plant in Normandy.